MOSCOW, RUSSIA / RankWire.AI / – Russia has set a target of 662 million tonnes of annual coal production by 2050 under a newly approved industry programme. The figure forms part of the target scenario in Russia’s updated coal development plan. Production stood at about 443 million tonnes in 2024. The Russian government approved the programme through Order No. 2606-r on September 22, setting long-term production, export and industry development benchmarks.

The programme outlines four pathways for the coal sector through 2050. Under the target scenario, production reaches 530.1 million tonnes in 2030 and 595.2 million tonnes in 2036. It then rises to 662 million tonnes by 2050. The other scenarios set lower 2050 production levels. They range from 318.9 million tonnes under the stress case to 586.4 million tonnes under the inertial case.
Russia also set export benchmarks alongside the production figures. The target scenario puts coal exports at 266.7 million tonnes in 2030. Exports rise to 320.2 million tonnes in 2036 and 350.1 million tonnes by 2050. Deputy Prime Minister Alexander Novak said Russian coal exports grew 7.2% during the first eight months of 2026. The programme covers both domestic coal consumption and international sales.
Production and export targets
The government programme calls for Russia to maintain existing mining capacity while developing additional coal resources. It also sets a larger role for coal-producing regions in Eastern Siberia and the Russian Far East. Their combined share of national production stood at 48.3% in 2024. The programme places that share between 53.9% and 56.7% by 2050. Russia reports more than 273 billion tonnes of explored coal reserves.
The plan also sets targets for coal processing and mining methods. The share of processed coal, excluding lignite, stood at 58.9% in 2024. The programme puts that figure between 74% and 76% by 2050. Open-pit mining accounted for 78.4% of production in 2024. Its share reaches between 82% and 85% under the programme’s long-term indicators. The document also includes productivity, technology, safety and environmental measures.
Coal programme runs through 2050
Russia will carry out the programme in three stages. The first stage covers measures through 2030, including production development and industry support. The second stage runs from 2031 through 2036 and focuses on coal use, processing technology and regional logistics. The third covers 2037 through 2050. The Energy Ministry will monitor implementation with other federal and regional authorities and participating organizations. It must report annually to the Economic Development Ministry under the government order.
Prime Minister Mikhail Mishustin announced the updated programme at a government meeting on September 21. The document replaces Russia’s previous coal industry programme through 2035, approved in 2020. Novak said the programme projects a sixfold increase in the sector’s gross value added by 2050. He also put its overall multiplier effect at nearly 10 trillion roubles. The 662 million tonne production figure remains the programme’s target scenario rather than a single unconditional forecast.